JMG Solar Project Targets ₦55m Annual Savings for First Patriot

0
59
JMG Solar Project Targets ₦55m Annual Savings for First Patriot

First Patriot Limited expects to save between ₦50 million and ₦55 million annually after installing a hybrid solar power system designed to reduce its dependence on diesel generators.

The lead and zinc mining and processing company previously relied on a 400 kVA diesel generator, with operating and maintenance costs estimated at about ₦8 million monthly.

JMG Solar, the renewable energy division of JMG Limited, installed a system combining a 250 kW solar inverter, 200 kWh lithium-ion battery storage and 280 kWp monocrystalline solar panels.

The installation works alongside First Patriot’s existing power sources, using solar energy during the day and battery storage and power management to meet demand and coordinate generator support when needed.

The system is also expected to reduce generator runtime and maintenance needs, improve power stability and lower the facility’s carbon emissions.

Rabi Jammal, Chief Commercial Officer of JMG Limited, said the project was intended to help the company reduce energy costs without disrupting production.

The project was delivered through JMG’s turnkey model, which covered engineering design, equipment supply, installation and commissioning.

Hybrid solar systems are increasingly being considered by businesses seeking to manage energy expenses amid high diesel costs and unreliable grid supply.